ARPA Project Update

2025 has been a busy year so far for RVSD. The drilling of the Madison Well was completed earlier this year, and despite the delays the quality and yeild of the well turned out to be phenomenal! This additional water source will provide for our customers well into the future!

Construction is back in progress for the new 2 million gallon storage tank after some time off during the winter months. The exterior painting will be starting soon and the tank should be complete by summer's end. 

Lastly, work has started on the well house for the Madison Well and we hope to have the well operational before the end of 2025!