ARPA Project Update

The contractor for our new 2 million gallon storage reservoir is getting ready to remobilize after shutting down for the winter. The estimated completion of the tank is summer 2025. 

The 12" water main to Box Elder for regional emergency use was completed on time in the fall of 2024.

The drilling of the Madison well was completed in February. We are in the process of water and pump testing for the well. Soon the construction on the well house will begin!